MaMeeFarm™ Analysis

When Electricity Generation Grows Faster Than Grid Capacity

Date: 25 October 2026

The world can build more electricity generation without making all of that capacity immediately usable.

Solar farms can be completed.

Wind projects can be financed.

Battery storage can be installed.

Data centres can be approved.

Factories can plan expansion.

But electricity still has to connect to a network, move through that network, and reach the place where it will be used.

This is becoming one of the central infrastructure challenges of the global electricity system.

More Than 2,500 GW of Projects Are Waiting in Connection Queues

The International Energy Agency estimates that more than 2,500 GW of projects are currently stalled in grid connection queues around the world.

That total includes renewable generation, electricity storage, and large electricity loads such as data centres.

The number requires careful interpretation.

It does not mean 2,500 GW of electricity is already being generated and wasted.

The projects are at different stages of development and are waiting for network capacity, grid studies, approvals, upgrades, or connection infrastructure.

The scale of the queue nevertheless demonstrates how important grid access has become.

Source: International Energy Agency, Electricity 2026.

The Grid Can Develop More Slowly Than Generation and Demand

One reason connection queues grow is that different parts of the electricity system develop on different timelines.

The IEA estimates that new solar and wind projects can typically be developed within approximately one to five years.

New data centres can sometimes be developed within one to three years.

Major grid infrastructure, however, can require approximately five to fifteen years for planning, permitting, and construction.

Electricity supply and large new loads can therefore appear faster than the networks needed to connect them.

Source: International Energy Agency, Electricity 2026.

Installed Generation Is Not the Same as Connected Capacity

A country can add substantial generation capacity while some projects still wait for grid access.

Connection can require substations, transmission upgrades, transformers, network studies, or additional local capacity.

The generation technology may be available.

Finance may be available.

Demand may be available.

But the surrounding network infrastructure can still delay economic use.

Grid Expansion Has Its Own Industrial Supply Chain

Building more electricity networks requires more than investment approval.

Transmission systems require physical equipment.

Transformers.

Cables.

Switchgear.

Substations.

Power electronics.

Those products also require factories, materials, specialist workers, and manufacturing capacity.

Grid expansion therefore depends on another industrial system behind the electricity network.

Critical Grid Equipment Can Take Years to Procure

Supply-chain pressure is already affecting transmission development.

The International Energy Agency reports that procurement for important transmission components has become substantially slower in recent years.

Cables can require approximately two to three years to procure.

Large power transformers can take up to four years.

Specialised direct-current cables can take even longer.

Planning a grid therefore does not mean every component required to build it is immediately available.

Source: International Energy Agency, Building the Future Transmission Grid.

Cable Manufacturing Is Becoming Part of the Bottleneck

The pressure is increasingly visible in cable manufacturing.

Reuters reported on 22 October that Nexans sees limited cable-production capacity becoming a bottleneck for AI-related data-centre development.

The company said constructing a new cross-linked polyethylene cable production line can take approximately three years.

Utilities are also moving toward longer procurement agreements to secure future supply.

This illustrates how rapidly expanding electricity demand can create pressure beyond the grid itself.

It can also pressure the manufacturing capacity needed to expand the grid.

Source: Reuters, 22 October 2026.

AI Data Centres Are Increasing the Pressure

Artificial intelligence is adding another source of electricity demand.

Large data centres can require substantial power concentrated in a single location.

Connecting such projects can require additional substations, transmission capacity, grid reinforcement, and generation.

In some parts of the United States, Reuters reported grid connection waits of approximately three to six years for data-centre projects.

Some developers are consequently exploring onsite generation, including fuel cells, while waiting for conventional grid connections.

Sources: Reuters, 23 October 2026; International Energy Agency.

National Generation Does Not Guarantee Local Grid Access

Electricity is highly dependent on location.

A country may possess substantial generation capacity while a particular industrial region or data-centre cluster still faces connection constraints.

Power has to move through specific network paths.

Local substations can reach capacity.

Transmission corridors can become congested.

Network reinforcement can take time.

Electricity availability therefore cannot be understood only through national generation totals.

Grid Congestion Has Economic Costs

When networks cannot move electricity efficiently, system operators may have to respond in other ways.

Generation can be curtailed.

More expensive power plants may need to operate.

Connections can be delayed.

Additional local generation or reserves may become necessary.

The International Energy Agency estimates that grid congestion already creates substantial costs in major electricity markets.

The electricity itself may be inexpensive.

Delivering it through a constrained system can still be costly.

Curtailment Makes the Difference Visible

Renewable generation can sometimes produce more power than the network can absorb or move at that moment.

When this happens, some potential generation may be curtailed.

The solar panels or wind turbines still exist.

The resource still exists.

But the network cannot fully use the available output.

This demonstrates why generation capacity and usable electricity capacity are not identical.

Storage Helps, but It Does Not Replace Transmission

Battery storage can help electricity systems manage periods of excess supply and high demand.

It can move electricity across time.

Transmission networks perform a different function.

They move electricity across geography.

A region producing abundant power may still need transmission infrastructure if the major demand is located elsewhere.

Storage and transmission therefore complement one another.

Some Electricity Demand Can Become More Flexible

Electricity users can also help reduce pressure on constrained networks.

Some large consumers may be able to shift certain activities away from the busiest periods.

Data centres, storage facilities, and other flexible resources may sometimes adjust operations in ways that improve network utilisation.

This can create additional room within existing infrastructure.

But flexibility does not eliminate the need for physical networks.

Existing Grids Can Sometimes Carry More Power

Expanding grid capacity does not always require building an entirely new transmission corridor.

The International Energy Agency identifies technologies that can improve the capacity of existing networks.

These include advanced conductors, dynamic line ratings, advanced power-flow control, reconductoring, and voltage upgrades.

IEA analysis estimates that grid-enhancing technologies and selected upgrades could create enough additional hosting capacity to connect approximately 450 to 700 GW of advanced-stage projects currently waiting in queues, under the assumptions used in its analysis.

These measures do not remove the need for new infrastructure.

They can help make better use of existing infrastructure while larger projects move forward.

Source: International Energy Agency, Electricity 2026.

Permitting and Coordination Also Affect the Timeline

Grid expansion is not only an engineering problem.

Transmission projects can cross multiple jurisdictions, communities, private properties, and environmentally sensitive areas.

Utilities, regulators, generators, industrial customers, equipment manufacturers, local governments, and landowners may all be involved.

Delays can therefore emerge even when the technology required for a project is well understood.

The International Energy Agency continues to identify permitting and supply-chain constraints as significant obstacles to faster transmission development.

Renewable Growth Can Increase the Need for Transmission

Renewable generation is not always located close to the largest centres of electricity demand.

Strong wind resources may be distant from cities.

Large solar projects may be distant from industrial centres.

This means a cleaner generation system can also require stronger networks capable of moving electricity over greater distances.

Transmission therefore becomes an essential part of integrating new generation.

The Grid Is Becoming Common Infrastructure for Several Economic Transitions

Electricity networks increasingly support many changes happening at once.

Renewable generation.

Electric vehicles.

Heat pumps.

Industrial electrification.

Battery storage.

Data centres.

The grid therefore sits beneath several major economic and technological transitions simultaneously.

Pressure on networks can consequently become pressure on industrial and economic development as well as on the energy system.

Grid Capacity Is Becoming an Industrial Location Issue

Electricity access increasingly influences where major industrial projects can develop.

A location may have suitable land, workers, logistics, and customers.

But a long wait for the required electricity connection can still delay or change an investment decision.

This makes grid capacity part of regional competitiveness and industrial development.

Both New Supply and New Demand Can Wait for the Same Network

The current grid challenge affects both sides of the electricity system.

New generation projects want to connect.

New factories want electricity.

New data centres want electricity.

Storage projects also need connections.

When all of them expand faster than network capacity, the grid can become the shared constraint between new supply and new economic demand.

A Connection Queue Is Not Automatically an Electricity Shortage

Long connection queues need to be interpreted carefully.

They do not necessarily mean that an economy lacks total electricity generation.

A country can possess significant power supply while individual projects compete for limited network access in specific locations.

The constraint can therefore be one of connection and delivery, rather than electricity generation itself.

Late Grid Investment Can Delay Economic Activity

When network expansion arrives too late, the economic consequences extend beyond the power sector.

Renewable projects can wait.

Industrial expansion can wait.

Data centres can wait.

Electrification can wait.

The cost is therefore not only an energy cost.

It can also become a delay in productive investment and economic capacity.

But More Grid Capacity Also Requires Long-Term Investment

Building electricity networks far ahead of actual demand also carries costs.

Transmission infrastructure is capital intensive and can operate for decades.

Costs are ultimately financed through utilities, investors, governments, or electricity users.

Grid expansion therefore requires forward-looking investment while future demand is still uncertain.

That challenge is inherent in long-lived infrastructure that takes years to develop.

The Grid Is Becoming an Economic-Capacity Issue

Global electricity demand is rising.

Renewable generation continues to expand.

AI-related data centres are adding large concentrated loads.

Manufacturing is becoming more electrified.

Transport is becoming more electrified.

All of these developments increase the importance of electricity networks.

The grid is no longer only an energy-sector issue.

It increasingly determines how quickly new economic capacity can become operational.

Conclusion

The global electricity system is expanding rapidly.

More renewable generation is being built.

More storage is being installed.

Data-centre demand is increasing.

Industrial electrification is expanding.

But the network connecting electricity supply with economic demand often develops more slowly.

More than 2,500 GW of generation, storage, and large-load projects are now in grid connection queues worldwide.

Major transmission infrastructure can take years longer to develop than many generation projects or data centres.

Critical equipment such as transformers and cables also faces long manufacturing and procurement timelines.

This does not mean electricity generation is failing.

It means that producing electricity and delivering usable power are different infrastructure challenges.

As electricity becomes increasingly important to manufacturing, artificial intelligence, transport, and the wider economy, grid capacity is becoming part of economic capacity itself.

Building generation remains essential.

But its full economic value increasingly depends on whether the network can connect it, move it, and deliver it where demand exists.


Author: P’Toh